top of page

CTE & TRADES · POSTSECONDARY CTE, APPRENTICESHIP, COLLEGE · 50 MINUTES

The Site Logistics Plan: Laydown, Trailers, Crane Reach and Fire Access lesson plan

Construction-management students tape a job-site logistics plan at reduced or full scale, check the fire lane, the crane's reach to the laydown yard and the trailer's position under the swing, and fix the plan before mobilization.

Free, no sign-up, and no print needed. A life-size floor print is optional: school prints are $0.45 per printed sq ft, $100 minimum.

On this page: Teach it in 5 steps · Learner card · Printable

Classroom setup sketch for The Site Logistics Plan (Laydown, Trailers, Crane Reach and Fire Access), showing the room layout, tape lines and team spots

At a glance

  • Time: 50 minutes

  • Level: Postsecondary CTE, apprenticeship, college

  • Subject: CTE & trades: Laydown, Trailers, Crane Reach and Fire Access

  • Grouping: Teams of 3: superintendent, fire marshal, crane operator.

  • Space: A gym at 1 ft = 10 ft, or a table with the print.

  • Included: Teacher script, scenario sheet, learner sheet, exit ticket and answer key with every number worked

Open the printable lesson: script, scenario, learner sheet and answer key (PDF) →


Teach it in 5 steps

The whole lesson on one screen. Details for each step are further down.

  1. Before class: Tape the lot, the 120 ft x 80 ft building, the crane at its mark, the trailer and the laydown at their as-drawn positions.

  2. Show them (5 min): Hook. "Trucks arrive Monday. What can go wrong with where we put things?"

  3. Try it together (10 min): Fire lane. Measure the clear width along the south side.

  4. Teams work (31 min): Run steps 3-5 of the procedure below: Crane reach → Under the swing → Fix.

  5. Check (4 min): Exit ticket: A crane at (0, 0) reaches 80 ft. Is a corner at (60, 50) in reach?


Learner card

Read this part with your class, or print it for each team.

Your challenge
The superintendent mobilizes Monday. Check the logistics plan the way the fire marshal and the crane operator will, and fix it before the trailer is set.

By the end, I can:

  • check a fire apparatus access lane for clear width

  • test whether a laydown area is inside a crane's reach

  • move site elements to clear every conflict

Who uses this
superintendents, project engineers and safety managers, who draw logistics plans before a job mobilizes.


Essential question

Where should everything go on a job site, and how do you prove it before the trucks arrive?


What learners learn and show

  • The big idea: A logistics plan is a set of distance checks: fire access width, crane reach to material, and people kept out from under loads.

  • Show it: a check sheet with the fire-lane width, the farthest laydown corner from the crane, the trailer's nearest point to the crane, and a fixed plan that passes.

Objectives

  • Measure the clear width of the fire lane.

  • Compute the distance from the crane to each laydown corner.

  • Compute the trailer's nearest distance to the crane.

  • Move the trailer and laydown so every check passes.


Materials and prep

  • A print of the 200 ft x 150 ft site (scale 1 in = 10 ft, or 1 ft = 10 ft taped in a gym)

  • String the length of the crane radius at your scale

  • Tape measures, calculators

  • The printable: scenario sheet and check sheet

Prep

  1. Tape the lot, the 120 ft x 80 ft building, the crane at its mark, the trailer and the laydown at their as-drawn positions.

  2. Cut a string to the crane radius at your scale and tie it at the crane.

  3. Print one check sheet per team.

Space: A gym at 1 ft = 10 ft, or a table with the print.

Grouping: Teams of 3: superintendent, fire marshal, crane operator.


Lesson procedure

  1. 0-5 min, Hook: "Trucks arrive Monday. What can go wrong with where we put things?" Ask: Who has to approve this plan? Listen for: The fire marshal, the crane operator, the owner.

  2. 5-15 min, Fire lane: Measure the clear width along the south side. Ask: Does the lane pass? Listen for: No: 18 ft clear; needs 20.

  3. 15-25 min, Crane reach: Swing the string from the crane to each laydown corner. Ask: Can the crane reach all of the laydown? Listen for: No: the far corner is 118 ft; reach is 90.

  4. 25-33 min, Under the swing: Measure from the crane to the trailer's nearest point. Ask: Is the trailer under the swing? Listen for: Yes: 82 ft, inside 90 ft.

  5. 33-46 min, Fix: Move the trailer and the laydown and re-check all three. Ask: What passes? Listen for: Laydown far corner 71 ft; trailer 94 ft from the crane; lane clear.

  6. 46-50 min, Exit ticket: Individual exit ticket.


Checks for understanding

  • Ask: Why check the farthest corner of the laydown, not the middle? Look for: If the far corner is in reach, all of it is.

  • Ask: Why keep an occupied trailer out from under the swing? Look for: People should not sit under suspended loads.

  • Ask: Why is the fire lane checked first? Look for: It is a code requirement the fire marshal enforces; the rest is planning.


Exit ticket

  1. A crane at (0, 0) reaches 80 ft. Is a corner at (60, 50) in reach? Answer: Yes: 78.1 ft.

  2. A trailer is 15 ft from the lot line along the fire lane. Does the lane pass at 20 ft? Answer: No: 5 ft short.

  3. Name one other thing a logistics plan shows. Answer: Gates, haul routes, parking, dumpsters, washout, toilets or fencing.

Scoring: 1 point each, plus 1 for a fixed plan with distances. 3 or more = secure.


Common misconceptions

  • Learners may think: The crane reaches anything it can see. Address it: Reach is a radius; material outside it must be moved twice.

  • Learners may think: The fire lane can be used for parking during the day. Address it: It must stay clear at all times.


Supports and extensions

Give a distance-formula card and a worked example.

Multilingual learners: label lane, laydown, trailer and crane on the floor with pictures.

Mobility: the string test works from a seat on a tabletop print.

Transfer task: Mark up a real logistics plan from a local project (or a published one) with the same three checks.


Why at full scale

Swinging a string from the crane mark makes reach and the swing zone visible to the whole team.


Codes, standards and frameworks

  • International Fire Code (IFC): 503.2.1 fire apparatus access roads: 20 ft unobstructed width (check the edition your jurisdiction adopted)

  • Perkins V (CTE): postsecondary and secondary CTE program context

Codes and standards change and are adopted locally. This lesson teaches the method; use the edition your jurisdiction or program has adopted.


Ready to teach it?

The printable has the teacher script, the scenario sheet, the learner sheet and the answer key. Open the printable lesson →

Need the floor plan itself? Get a 1:1 print quote.


Paying for the print? Use a grant

Many teachers fund the 1:1 print with Perkins V career and technical education funds. Start from From Drawing to Takeoff: a construction-trades pathway on life-size plans, our grades 9-12 CTE grant packet, and add this lesson to its timetable. The packet has a project description, measurable objectives, a lesson timetable, an evaluation plan, a budget and a principal letter, written to the questions funders ask.

Download the grant packet (PDF) · Editable Word version · All funding options


Related lessons

More in the College & Trades track: The MacLeamy Curve · The Pre-Pour Walk · The Slab Takeoff · Square the Layout · Receptacle Layout to Code · Measure It Like an Appraiser · Walk the Patient Room · The Owner Walk · Equipment Footprints and Service Clearances · Space Planning Review · Occupant Load and Exits · Plan the Sales Floor · Set the Banquet Room · Walk the Kitchen Line · Check the Toilet Room · The Tenant Test Fit · Lab Safety Layout · Lay Out the Stair · Place the Smoke Alarms · Plan the Child Care Room · Rack the Warehouse · Lay Out the Parking Lot · Roof Takeoff from the Plan · Space the Sprinkler Heads · Lay Out the Tile

Browse all 100 floor plan lesson plans · Standards map

bottom of page