CTE & TRADES · POSTSECONDARY CTE, APPRENTICESHIP, COLLEGE · 50 MINUTES

Roof Takeoff from the Plan: Pitch Factor, Roofing Squares, Bundles and Drip Edge lesson plan

Roofing and construction-estimating students take off a gable roof from the Teaching House plan: walk the eave line on the full-size print, apply the pitch factor, and order shingles and drip edge.

Free, no sign-up, and no print needed. A life-size floor print is optional: school prints are $0.45 per printed sq ft, $100 minimum.

Classroom setup sketch for Roof Takeoff from the Plan (Pitch Factor, Roofing Squares, Bundles and Drip Edge), showing the room layout, tape lines and team spots

At a glance

  • Time: 50 minutes

  • Level: Postsecondary CTE, apprenticeship, college

  • Subject: CTE & trades: Pitch Factor, Roofing Squares, Bundles and Drip Edge

  • Grouping: Teams of 3: estimator, roofer, recorder.

  • Space: The TP-01 1:1 print with room to walk 1 ft outside it, or the plan pages at desks.

  • Included: Teacher script, scenario sheet, learner sheet, exit ticket and answer key with every number worked

Open the printable lesson: script, scenario, learner sheet and answer key (PDF) →


For learners

Your challenge: The roofer needs an order by noon. Take the roof off the Teaching House plan, from the footprint to the bundle count, and show every step.

By the end, I can:

  • find roof area from a footprint, overhang and pitch

  • convert area to squares and bundles with waste

  • measure eave and rake lengths for drip edge

Who uses this: roofers, estimators and construction managers, who order roofing from the plan before the trusses are set.


Essential question

How do you buy a sloped roof from a flat plan?


What learners learn and show

Learn: A plan shows the roof flat; the pitch factor turns the flat run into the sloped length that gets shingled.

Show: a takeoff sheet with eave length, run, pitch factor, roof area, squares, the order with waste, bundles and drip edge pieces.

Objectives

  • Find the eave length and horizontal run with the overhang.

  • Find the pitch factor for a 6/12 roof.

  • Compute roof area, squares and bundles with waste.

  • Measure and order drip edge.


Materials and prep

  • The Teaching House (TP-01) plan pages or the 1:1 print

  • Tape measures, a framing square

  • Calculators

  • The printable: scenario sheet and takeoff sheet

Prep

  1. Roll out the TP-01 print; tape a line 1 ft outside the exterior walls for the eaves.

  2. Tape a 6/12 triangle on the floor: 12 in run, 6 in rise.

  3. Print one takeoff sheet per team.

Space: The TP-01 1:1 print with room to walk 1 ft outside it, or the plan pages at desks.

Grouping: Teams of 3: estimator, roofer, recorder.


Lesson procedure

  1. 0-5 min, Hook: "The plan is flat. The roof is not. How do you order shingles?" Ask: What is missing from the plan? Listen for: The slope.

  2. 5-15 min, Walk the eaves: Walk the eave line 1 ft outside the walls. Eave 58 ft; run per side 22 ft. Ask: Why add the overhang? Listen for: The roof extends past the walls.

  3. 15-25 min, Pitch factor: Measure the taped 6/12 triangle: 12 in run, 6 in rise, slope? Ask: Pitch factor? Listen for: 1.118: about 13.4 in of slope per 12 in of run.

  4. 25-40 min, Area and order: Area = 2 x 58 x 24.60. Squares, +10% waste, 3 bundles per square. Ask: Order? Listen for: 28.53 squares, order 32, 96 bundles.

  5. 40-45 min, Drip edge: Eaves plus rakes, in 10-ft pieces. Ask: Pieces? Listen for: 214.4 ft: 22 pieces.

  6. 45-50 min, Exit ticket: Individual exit ticket.


Checks for understanding

  • Ask: Why is the roof bigger than the footprint? Look for: Overhang adds width and length; slope adds length up the roof.

  • Ask: What is a square? Look for: 100 sq ft of roof.

  • Ask: Why round the order up? Look for: You can't buy part of a square, and waste is real.


Exit ticket

  1. Flat run 20 ft, pitch factor 1.118. Sloped length? Answer: 22.36 ft.

  2. 2,400 sq ft of roof plus 10% waste. Squares to order? Answer: 27 (26.4 rounded up).

  3. 27 squares at 3 bundles each? Answer: 81 bundles.

Scoring: 1 point each, plus 1 for a complete takeoff. 3 or more = secure.


Common misconceptions

  • Learners may think: Roof area equals the floor area. Address it: The roof here is 2,853 sq ft over a 2,352 sq ft footprint: overhang and slope add area.

  • Learners may think: Pitch factor multiplies both directions. Address it: It stretches only the slope direction; the eave length stays the same.


Supports and extensions

Give a formula card: factor = square root of (1 + (rise / 12) squared).

Multilingual learners: label eave, rake, ridge, run and pitch on the print.

Mobility: the estimator works the math from a seat; teammates walk the eave line.

Transfer task: Estimate the roof of a building on campus from its footprint and an assumed pitch.


Why at full scale

Walking the eave line outside the full-size walls shows where the overhang adds roof that a footprint area misses.


Codes, standards and frameworks

  • Scenario rules: gable roof, 6/12 pitch, 12-in overhang, 10% waste and 3 bundles per square are scenario values; follow the shingle maker's coverage on the bundle

  • Perkins V (CTE): postsecondary and secondary CTE program context

Codes and standards change and are adopted locally. This lesson teaches the method; use the edition your jurisdiction or program has adopted.


Ready to teach it?

The printable has the teacher script, the scenario sheet, the learner sheet and the answer key. Open the printable lesson →

Need the floor plan itself? This lesson works with the free Teaching House plan: printed 1:1 it is about $1,100. Delivery to your ZIP is added on your quote. Purchase orders welcome. Get a 1:1 print quote.


Paying for the print? Use a grant

Many teachers fund the 1:1 print with Perkins V career and technical education funds. Start from From Drawing to Takeoff: a construction-trades pathway on life-size plans, our grades 9-12 CTE grant packet, and add this lesson to its timetable. The packet has a project description, measurable objectives, a lesson timetable, an evaluation plan, a budget and a principal letter, written to the questions funders ask.

Download the grant packet (PDF) · Editable Word version · All funding options


Related lessons

More in the College & Trades track: The MacLeamy Curve · The Pre-Pour Walk · The Slab Takeoff · Square the Layout · Receptacle Layout to Code · Measure It Like an Appraiser · Walk the Patient Room · The Owner Walk · Equipment Footprints and Service Clearances · Space Planning Review · Occupant Load and Exits · Plan the Sales Floor · Set the Banquet Room · The Site Logistics Plan · Walk the Kitchen Line · Check the Toilet Room · The Tenant Test Fit · Lab Safety Layout · Lay Out the Stair · Place the Smoke Alarms · Plan the Child Care Room · Rack the Warehouse · Lay Out the Parking Lot · Space the Sprinkler Heads · Lay Out the Tile

Browse all 100 floor plan lesson plans · Standards map