Occupant Load and Exits: Occupant Load, Exit Count, Egress Width and Exit Separation lesson plan

Fire-science, architecture and construction students tape a multipurpose room at full size, compute its occupant load two ways, then check exit count, door width and how far apart the exits are, and fix what fails.

Free, no sign-up, and no print needed. A life-size floor print is optional: school prints are $0.45 per printed sq ft, $100 minimum.

On this page: Teach it in 5 steps · Learner card · Printable

Classroom setup sketch for Occupant Load and Exits (Occupant Load, Exit Count, Egress Width and Exit Separation), showing the room layout, tape lines and team spots

At a glance

  • Time: 50 minutes

  • Level: Postsecondary CTE, apprenticeship, college

  • Subject: CTE & trades: Occupant Load, Exit Count, Egress Width and Exit Separation

  • Grouping: Teams of 3.

  • Space: A gym or a 48 ft x 60 ft area; the print can be used at a smaller scale on a classroom floor.

  • Included: Teacher script, scenario sheet, learner sheet, exit ticket and answer key with every number worked

Open the printable lesson: script, scenario, learner sheet and answer key (PDF) →


Teach it in 5 steps

The whole lesson on one screen. Details for each step are further down.

  1. Before class: Tape the 48 ft x 60 ft room.

  2. Show them (5 min): Hook. "Banquet tonight, concert next month. Same room. Same capacity?"

  3. Try it together (10 min): Net area. Measure the room and the stage; compute net area.

  4. Teams work (30 min): Run steps 3-5 of the procedure below: Two loads → Doors → Separation.

  5. Check (5 min): Exit ticket: A room has 1,500 sq ft net, chairs only (7 sq ft net each). Occupant load?


Learner card

Read this part with your class, or print it for each team.

Your challenge
The school wants to seat a banquet tonight and a concert next month in the same room. Find how many people each setup holds and whether the doors as built can let them out.

By the end, I can:

  • compute occupant load from net area and a load factor

  • check exit count, egress width and exit separation

  • propose the smallest change that makes the room pass

Who uses this
fire inspectors, fire-protection engineers, architects and facility managers, who set and post room capacities.


Essential question

How many people can a room safely hold, and what decides it: the floor or the doors?


What learners learn and show

  • The big idea: Occupant load comes from net area and how the room is used; the doors then have to be wide enough and far enough apart for that load.

  • Show it: a calculation sheet with both occupant loads, the exit count, required and provided egress width, the exit separation check, and a fix.

Objectives

  • Compute net area and occupant load for tables-and-chairs and for chairs-only use.

  • Find the number of exits required.

  • Compare required egress width with the clear width of the doors.

  • Check that the exits are far enough apart, and fix the room.


Materials and prep

  • A 1:1 print of a 48 ft x 60 ft multipurpose room, or its outline taped in a gym

  • Tape measures, a long tape for the diagonal

  • Calculators

  • The printable: scenario sheet and calculation sheet

Prep

  1. Tape the 48 ft x 60 ft room. Tape a 12 ft x 24 ft stage on the east wall.

  2. Mark door A on the west wall 10 ft from the south corner and door B on the west wall 40 ft from it.

  3. Print one calculation sheet per team.

Space: A gym or a 48 ft x 60 ft area; the print can be used at a smaller scale on a classroom floor.

Grouping: Teams of 3.


Lesson procedure

  1. 0-5 min, Hook: "Banquet tonight, concert next month. Same room. Same capacity?" Ask: What changes between the two? Listen for: How tightly people are packed: tables versus rows of chairs.

  2. 5-15 min, Net area: Measure the room and the stage; compute net area. Ask: Why take out the stage? Listen for: The scenario counts it separately; the floor load is the audience area.

  3. 15-25 min, Two loads: Divide net area by 15 (tables and chairs) and by 7 (chairs only). Round up. Ask: What are the two loads? Listen for: 173 and 371.

  4. 25-35 min, Doors: Count exits needed; compute required width at 0.2 in per person; measure the doors. Ask: Do two doors give enough width for the concert? Listen for: No: 74.2 in needed, 66 in provided.

  5. 35-45 min, Separation: Measure the diagonal and the distance between the doors. Ask: Are the doors far enough apart? Listen for: Not without sprinklers: 30 ft apart, half the diagonal is 38.4 ft.

  6. 45-50 min, Exit ticket: Individual exit ticket.


Checks for understanding

  • Ask: Why round occupant load up, never down? Look for: A fraction of a person is still a person the exits must serve.

  • Ask: Why does the concert fail on width when the banquet passes? Look for: The same doors serve more than twice as many people.

  • Ask: Why must exits be far apart? Look for: One fire or blockage should not cut off both.


Exit ticket

  1. A room has 1,500 sq ft net, chairs only (7 sq ft net each). Occupant load? Answer: 215 (1,500 / 7 = 214.3, round up).

  2. 215 occupants at 0.2 in each: required egress width? Answer: 43 in.

  3. A room's diagonal is 80 ft, unsprinklered. Minimum distance between two exits? Answer: 40 ft (half the diagonal).

Scoring: 1 point each, plus 1 for a correct fix with numbers. 3 or more = secure.


Common misconceptions

  • Learners may think: Capacity is set by the floor area alone. Address it: The floor allows 371 for a concert, but the doors as built only serve 330.

  • Learners may think: Two doors anywhere count as two exits. Address it: Doors close together can both be blocked by one fire; the separation rule decides.


Supports and extensions

Give a formula card: net area / factor; occupants x 0.2 in; diagonal / 2 or / 3.

Multilingual learners: label net area, occupant, exit and egress on the floor with pictures.

Mobility: the diagonal and door measurements can be read from the print by a seated teammate.

Transfer task: Find the posted capacity sign in a room on campus and check it against its area and doors.


Why at full scale

Walking from door A to door B and along the diagonal shows why separation matters in a way a drawing does not.


Codes, standards and frameworks

  • International Building Code (IBC): Table 1004.5 occupant load factors (assembly unconcentrated 15 net, concentrated 7 net); Table 1006.3.3 (1-500 occupants: 2 exits); 1005.3.2 (0.2 in per occupant); 1007.1.1 exit separation (check the edition your jurisdiction adopted)

  • Perkins V (CTE): postsecondary and secondary CTE program context

Codes and standards change and are adopted locally. This lesson teaches the method; use the edition your jurisdiction or program has adopted.


Ready to teach it?

The printable has the teacher script, the scenario sheet, the learner sheet and the answer key. Open the printable lesson →

Need the floor plan itself? Get a 1:1 print quote.


Paying for the print? Use a grant

Many teachers fund the 1:1 print with Perkins V career and technical education funds. Start from From Drawing to Takeoff: a construction-trades pathway on life-size plans, our grades 9-12 CTE grant packet, and add this lesson to its timetable. The packet has a project description, measurable objectives, a lesson timetable, an evaluation plan, a budget and a principal letter, written to the questions funders ask.

Download the grant packet (PDF) · Editable Word version · All funding options


Related lessons

More in the College & Trades track: The MacLeamy Curve · The Pre-Pour Walk · The Slab Takeoff · Square the Layout · Receptacle Layout to Code · Measure It Like an Appraiser · Walk the Patient Room · The Owner Walk · Equipment Footprints and Service Clearances · Space Planning Review · Plan the Sales Floor · Set the Banquet Room · The Site Logistics Plan · Walk the Kitchen Line · Check the Toilet Room · The Tenant Test Fit · Lab Safety Layout · Lay Out the Stair · Place the Smoke Alarms · Plan the Child Care Room · Rack the Warehouse · Lay Out the Parking Lot · Roof Takeoff from the Plan · Space the Sprinkler Heads · Lay Out the Tile

Browse all 100 floor plan lesson plans · Standards map

bottom of page