CTE & TRADES · POSTSECONDARY CTE, APPRENTICESHIP, COLLEGE · 50-60 MINUTES
The Owner Walk: Finding Changes Early and Pricing Them by Phase lesson plan
Construction-management and architecture students host an owner walk on a full-size plan, capture every change, then price each one at design, after framing and after drywall to see what waiting costs.
Free, no sign-up, and no print needed. A life-size floor print is optional: school prints are $0.45 per printed sq ft, $100 minimum.
On this page: Teach it in 5 steps · Learner card · Printable

At a glance
Time: 50-60 minutes
Level: Postsecondary CTE, apprenticeship, college
Subject: CTE & trades: Finding Changes Early and Pricing Them by Phase
Grouping: Teams of 3: PM, estimator, recorder; one owner for the class.
Space: The full plan, or the four areas taped at full size in a gym.
Included: Teacher script, scenario sheet, learner sheet, exit ticket and answer key with every number worked
Open the printable lesson: script, scenario, learner sheet and answer key (PDF) →
Teach it in 5 steps
The whole lesson on one screen. Details for each step are further down.
Before class: Roll out or tape the clinic suite with exam room 3, the 20-ft clinical corridor at 44 in, the staff room and the lab and storage rooms.
Show them (5 min): Hook. "Today the owner walks the plan. Every comment is cheap now and expensive later. How expensive?"
Try it together (15 min): Owner walk. The owner walks the plan and raises four changes.
Teams work (30 min): Run steps 3-4 of the procedure below: Price by phase → Totals and the multiple.
Check (5 min): Exit ticket: A change takes 2 design hours at $150. After framing it adds 5 hours at $95 and $100 of material. Cost after framing?
Learner card
Read this part with your class, or print it for each team.
Your challenge
The owner walks the clinic layout today. Every change they find now is a redraw; the same change after drywall is a demolition. Price both and tell the owner what waiting would cost.
By the end, I can:
log owner changes as clear, priceable items
price a change at three phases from stated rates
explain the cost of late change with numbers
Who uses this
project managers, project engineers, architects and owners' representatives, who run walkthroughs and price changes.
Essential question
Why does the same change cost more the later you find it, and how do you prove it to an owner?
What learners learn and show
The big idea: A change found on a full-size layout during design costs a redraw; the same change after framing adds rework, and after drywall adds demolition and refinishing, so early walks save real money.
Show it: a change log with four priced changes at three phases, totals, and the multiple between finding them now and after drywall.
Objectives
Write each owner comment as a change: what, where, why.
Price each change at design, after framing and after drywall from the stated rates.
Total the three phases and compute how many times more the late changes cost.
Recommend which changes to approve now.
Materials and prep
A 1:1 print of a clinic suite, or its key rooms taped on the floor
The printable: scenario sheet with the change list and rates, and the change log
Calculators
Prep
Roll out or tape the clinic suite with exam room 3, the 20-ft clinical corridor at 44 in, the staff room and the lab and storage rooms.
Choose one student or the teacher to play the owner, with the four changes on a card.
Print one change log per team.
Space: The full plan, or the four areas taped at full size in a gym.
Grouping: Teams of 3: PM, estimator, recorder; one owner for the class.
Lesson procedure
0-5 min, Hook: "Today the owner walks the plan. Every comment is cheap now and expensive later. How expensive?" Ask: When would a change be cheapest? Listen for: Before anything is built.
5-20 min, Owner walk: The owner walks the plan and raises four changes. Teams log each one: what, where, why. Ask: Is each change specific enough to price? Listen for: Yes when it names the room, the element and the dimension.
20-40 min, Price by phase: Teams price each change at design, after framing and after drywall using the scenario rates. Ask: Which change grows the most? Listen for: C2, the corridor: the longest wall run.
40-50 min, Totals and the multiple: Teams total each phase and divide late by early. Ask: How many times more after drywall? Listen for: About 5.6 times the design-phase cost.
50-55 min, Exit ticket: Individual exit ticket.
Checks for understanding
Ask: Why is the window's unit cost in every phase? Look for: You buy the window whenever you decide; only the labor to make the opening grows.
Ask: Why does "after drywall" include the framing cost too? Look for: You still reframe, then patch, tape and paint on top of it.
Ask: What makes an owner comment priceable? Look for: Room, element, dimension and the reason.
Exit ticket
A change takes 2 design hours at $150. After framing it adds 5 hours at $95 and $100 of material. Cost after framing? Answer: $300 + $475 + $100 = $875.
Design total is $1,000 and after-drywall total is $6,000. How many times more? Answer: 6 times.
Name one reason to walk at full size rather than review drawings. Answer: People judge size and distance on foot; they catch what they would not see on paper.
Scoring: 1 point each, plus 1 for showing the phase math. 3 or more = secure.
Common misconceptions
Learners may think: Changes cost the same whenever you make them. Address it: In this scenario the same four changes cost $2,075 at design and $11,655 after drywall.
Learners may think: The owner should wait until they can see the real rooms. Address it: The full-size walk is seeing the real room, while it is still a drawing.
Supports and extensions
Give a filled example row for C1 and a blank for the rest.
Multilingual learners: label change, phase, labor and material on the sheet with icons.
Mobility: the owner role can be played seated, pointing on the plan.
Transfer task: Run the same walk on a real project drawing set and price two changes with your local rates.
Why at full scale
The owner walk happens on the floor at full size, the way design teams do it with a 1:1 print before construction.
Codes, standards and frameworks
The MacLeamy Curve (Big Floor Plans short class): the idea that the ability to change design falls and the cost of change rises over a project
Perkins V (CTE): postsecondary and secondary CTE program context
Codes and standards change and are adopted locally. This lesson teaches the method; use the edition your jurisdiction or program has adopted.
Ready to teach it?
The printable has the teacher script, the scenario sheet, the learner sheet and the answer key. Open the printable lesson →
Need the floor plan itself? Get a 1:1 print quote.
Paying for the print? Use a grant
Many teachers fund the 1:1 print with Perkins V career and technical education funds. Start from From Drawing to Takeoff: a construction-trades pathway on life-size plans, our grades 9-12 CTE grant packet, and add this lesson to its timetable. The packet has a project description, measurable objectives, a lesson timetable, an evaluation plan, a budget and a principal letter, written to the questions funders ask.
Download the grant packet (PDF) · Editable Word version · All funding options
Related lessons
Red-Line Review · Markups, RFIs and Revisions, Grades 9-12, CTE, University
The Revision Loop · Architecture & Engineering, University
What Is Spatial Validation? · Design & Engineering, Grades 6-8, Grades 9-12
More in the College & Trades track: The MacLeamy Curve · The Pre-Pour Walk · The Slab Takeoff · Square the Layout · Receptacle Layout to Code · Measure It Like an Appraiser · Walk the Patient Room · Equipment Footprints and Service Clearances · Space Planning Review · Occupant Load and Exits · Plan the Sales Floor · Set the Banquet Room · The Site Logistics Plan · Walk the Kitchen Line · Check the Toilet Room · The Tenant Test Fit · Lab Safety Layout · Lay Out the Stair · Place the Smoke Alarms · Plan the Child Care Room · Rack the Warehouse · Lay Out the Parking Lot · Roof Takeoff from the Plan · Space the Sprinkler Heads · Lay Out the Tile